What is a recommended strategy for a risk identified at the project onset that could negatively affect the project?

Prepare for the iQMS Business Process Services Test. Enhance your skills with interactive questions and comprehensive explanations. Conquer your exam with confidence!

When addressing a risk identified at the onset of a project, transferring the risk is a recommended strategy in various contexts. This approach involves shifting the responsibility and impact of the risk to a third party, often through contracts, insurance, or outsourcing. By doing so, the project team mitigates the potential negative effects that the risk could impose on the project.

This strategy is particularly beneficial because it relieves the project of potential burdens while still acknowledging that the risk exists. For example, if a project has financial risks associated with delays, the team might choose to transfer this risk to a contractor who would then assume responsibility for meeting specific timelines. This can enhance project stability and allow the project team to focus on their core objectives without being distracted by uncertainties.

In contrast, options like acceptance, reduction, or avoidance might not provide the same level of security from a risk perspective. Acceptance means acknowledging the risk but deciding to proceed regardless, which may lead to severe consequences if the risk materializes. Reduction implies taking steps to lessen the impact or likelihood of the risk but does not eliminate it. Avoidance seeks to eliminate the risk entirely, which is not always feasible or practical in every project scenario. Therefore, transferring the risk stands out as a proactive strategy capable of safeguarding

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy